Situation
Company X produces packaging
materials and is part of a larger organisation with sites all over the world.
The implementation of BPCS started in 1998. BPCS is an ERP application, developed
and delivered by SSA, an American software house, and belongs to the larger
ERP systems in the world.
The production process exists out of the extrusion of semi-manufactured products
and the converting of these semi-manufactured products to end products. The
raw materials for the extrusion process are issued in bulk. An important functionality
for the Planning & Control Department is the registration of the machine
hours, inclusive the downtime, and the waste material registration.
Problem
The registration of the
used raw materials has to be done according to a specific formula that back-flushes
the components based on the average output, the actual usage and the the component
list. BPCS doesn't offer a possibility to do this automatically. That is why
company X was forced to do it manually. Due to the large numbers and complexity
of the formula, this is a time consuming job.
The standard functionality of BPCS offers the possibilities to register the
machine hours and the waste materials, however this is a labour-intensive
job.
Mission
Develop a customized application against low costs and with less influence on the standard application.
Result
After the consultant
of De Moer Project Services visualised himself of the way of processing and
the problems, he made, in cooperation with the company, a set-up of how the
registration of the machine hours and the waste material can be done as easy
as possible. The focus was on the simplicity of input and the integration
of the several parts.
The next step was to find a solution to integrate the developed application
with the standard BPCS application. Due to the complexity of the concerning
BPCS modules, it was practical not possibly to re-engineer the standard functions
to the designed set-up. On advise of De Moer Project Services, the company
choose to use the BPCS EDI functionality. The final solution is an application
for inserting the data on an easy and quick way. Due to the Semantic Gateways,
present in the BPCS EDI module, it is now possible to sent the data to BPCS
and process it as if it was inserted directly with the standard BPCS functions.
With this solution De Moer Project Services fulfilled the mission. Due to
the short realisation time the cost could be kept relative low. By using the
standard BPCS functions, the impact on the standard application was nil.